Monday, April 18, 2016

Update 4/14/2016

Thursday during the construction meeting, our builders told us that we are ahead of schedule.  Last week you noticed as you walked or drove by, cement trucks pouring the foundation.  The foundation was finished Thursday! Yippee!!  Also, it was confirmed that masonry and brick work will begin the first week of May.



Thursday, April 14, 2016

The Latest

Hi all.  Hope you all enjoyed Spring break.  Our construction team worked throughout the week.  As you walk or drive by, you will see rebar and cement.  I have word from the supervisor that the brick laying will start around May 2nd.  We are so excited about that.  They are a little ahead of schedule.  That is also good news.  We will have more information after our meeting with them today at 1:30.  Also for your information, we have plans up in our office window so you can see what the school will look like on the inside.